STEPS IN APPLYING FOR A SERVICE CONNECTION

1. Go to your respective zone office.
2. Attend the Pre-Membership Orientation (PMO).
3. Secure all the requirements.
4. Fill-up necessary forms.
5. Pay the fees

REQUIREMENTS

Application for Membership (2 copies)

 

             -  1x1 ID picture
              - Pre-Membership Orientation Certificate
  

 

                          From Local Government Unit:

                          - Electrical Permit
                   
Certificate of Final Inspection/Completion
                          - 
Electrical Sketch - 1-9 outlets or 4kw below
                         
Electrical Plan - 10 outlets or kw & above
                          - 
Application for Temporary Service Connection (for temporary connection only)

Application for Membership (2 copies)

 

  

- Properly accomplished forms
Names of (2) nearest neighbor with corresponding account numbers
Tapping pole number (if missing prepare sketch)
 - Location Plan
Schedule of Load (to be filled-up by the Person-In-Charge of Installation)
1x1 ID picture
Valid IDs (SSS, Pag-ibig, Driver’s License, etc.)
Barangay Certification
Community Tax Certificate/Residence Certificate
Service Connection Agreement
Notarized Certificate of Undertaking (for tenants, contractor, caretaker)
Application for Membership and Electric Service Connection
- Temporary lighting contract (for temporary connection only)